The challenge for ETT
The difficulty was severalfold :
Manage temperature and humidity in several rooms, with regulation based on an average of sensors on the return air and variable flow boxes.
Varying the airflow rate (2,000 m3/h -> 5,000 m3/h) on a ‘RE’ type machine without causing major disruption in terms of pressure in each room. This meant that we had to install 2 refrigeration circuits with power modulation on each circuit to ensure that the thermodynamics worked properly.
Transport the 5 blocks with the possibility of tilting them by more than 45°, so all the blocks are reinforced and the compressor is delivered on a pallet.
Connection by ETT services.
The custom-built machine meant a long lead time, so we had to anticipate the purchase of components by bringing forward the design phase

Our approach
Our approach on this project was to respond with 1 single machine to manage all the rooms, while being very responsive in our responses (project and execution phases).

This project was a real challenge for ETT and no doubt for all the parties involved, firstly because of its accessibility, secondly because of the need to vary the supply air rate on a ‘RE’ type machine without disturbing the pressure in the various rooms, and thirdly because of the need to manage the temperature/hygrometry of several rooms.
Numerous meetings were held with the customer during the project and execution phases, and we were thanked for our responsiveness.